Laying terastone is no different to the method used for other materials to be glued to the floor.

 
A Firstly, lay concrete on the area to be covered, making sure that it is perfectly evened and levelled.
B Once the concrete is dry, pour on a layer of adhesive cement and place the tiles on top.
C The tiles should be completely level, with no protrusions.
D Once the tiles have been laid and after waiting 24 hours, pour the grout over the tiles. The grout should be similar in colour to that of the tiles.
E Once the grout has been poured over the flooring, make sure the joints between each tile are completely filled, using a rubber brush.
F Before the grout has dried, sprinkle on dry cement powder, rub the area using a scrubbing brush (or similar) and sweep clean.

 
   

Maintaining terastone

terastone JIMESA is easy to maintain. Use any cleaning product that is non-corrosive (do not use bleaches, ammonia, nitric acid, etc.).

We advise you to dilute the cleaning products in water, following the manufacturer's recommendations.